WA Public Transport Authority
Butler Extension Project Passenger Information Works
AwardedRequest for Tender
Details
Awarded
Description
The Contractor shall undertake the:
• Relocation, installation, testing and commissioning of the two existing Clarkson Platform 2 Platform Information Displays (PID’s) to Warwick Platform 2;
• Relocation, installation, testing and commissioning of the two existing Warwick Platform 2 PID’s to Clarkson Platform 2;
• Relocation, installation, testing and commissioning of the existing Clarkson Concourse Information Display (CID) to Butler;
• Installation, testing and commissioning of a new four line CID at Clarkson;
• Installation, testing and commissioning of two new four line double sided PID‘s at Butler;
• Supply, installation, testing and commissioning of six new two line Bus Information Displays (BID‘s) at Butler Station;
• Termination of all power, data and facilities cabling at each of the CIS Displays;
• Installation, testing and commissioning of a new Station Controller (Passenger Information Terminal or ‘PIT’) and a new Display Terminal Server in the PIN/PA Rack at Butler Station;
• Supply and installation of all optic fibre patching of the Station CIS Server equipment to the CIS Information Patch Panel in the PIN/PA Equipment Rack and to the IT Ethernet Network Switch in the IT/SCADA Equipment Rack;
• Supply and installation of any other required hardware or cabling to deliver complete and fully operational Customer Information Systems at Butler, Clarkson and Warwick Stations;
• Relocation, installation, testing and commissioning of the two existing Clarkson Platform 2 Platform Information Displays (PID’s) to Warwick Platform 2;
• Relocation, installation, testing and commissioning of the two existing Warwick Platform 2 PID’s to Clarkson Platform 2;
• Relocation, installation, testing and commissioning of the existing Clarkson Concourse Information Display (CID) to Butler;
• Installation, testing and commissioning of a new four line CID at Clarkson;
• Installation, testing and commissioning of two new four line double sided PID‘s at Butler;
• Supply, installation, testing and commissioning of six new two line Bus Information Displays (BID‘s) at Butler Station;
• Termination of all power, data and facilities cabling at each of the CIS Displays;
• Installation, testing and commissioning of a new Station Controller (Passenger Information Terminal or ‘PIT’) and a new Display Terminal Server in the PIN/PA Rack at Butler Station;
• Supply and installation of all optic fibre patching of the Station CIS Server equipment to the CIS Information Patch Panel in the PIN/PA Equipment Rack and to the IT Ethernet Network Switch in the IT/SCADA Equipment Rack;
• Supply and installation of any other required hardware or cabling to deliver complete and fully operational Customer Information Systems at Butler, Clarkson and Warwick Stations;
TenderHub gathers information continuously from a variety of sources. There may be delays between information being updated at the source and presented here. Always check with the source if you are concerned about currency or accuracy.
Key details
- Source
- Tenders WA
Briefings & site visits
No briefings or site visits were listed for this tender.
Awarded suppliers
1Contract awarded
$370,836 awarded to 1 supplier
Remote Monitoring Solutions (Milford Holdings)
$370,836