Description
Description
A project to be undertaken
Description of the goods and services to be provided
- Approximately 2.5 km twin metro railway tunnels, including mined cross passages - Excavation of a mined crossover cavern at the West of Pymont station site - Pyrmont station station mined cavern excavation - Hunter Street station mined cavern excavation - Turnback tunnels and mined cavern to the East of Hunter Street (Sydney CBD) station site At Pyrmont and Hunter Street station sites, works will also include: - Demolition of all existing building/structures - The provision of cast in situ concrete linings for all mined station caverns, adites and nozzle enlargements and - Anciliary works including utility services works and minor road works
TenderHub gathers information continuously from a variety of sources. There may be delays between information being updated at the source and presented here. Always check with the source if you are concerned about currency or accuracy.
Key details
- Buyer
- Sydney Metro
- Source
- Buy NSW
Briefings & site visits
No briefings or site visits were listed for this tender.
Awarded suppliers
1Contract awarded
$2,149,251,724 awarded to 1 supplier
CPB CONTRACTORS PTY LIMITED & GHELLA PTY LTD & JOHN HOLLAND PTY LTD
$2,149,251,724
ABN 77863045764
LEVEL 6 60 Union Street Sydney nsw 2009 AU
See who else bid on this tender
Subscribers see every supplier who bid on this tender, plus its change history and a direct link to the source notice.