The full project involves the rehabilitation of existing concrete piles to the Bowen Road Bridge. There are 16 piers, with 14 piles per pier and works are to be in accordance with CN-9285 contract documentation and drawings and TMR technical specifications.
RoadTek are required to construct a suitable bund that will allow the works to be undertaken. This contract is for the supply, installation and removal of sheet piles.
All works and materials shall be in accordance with the relevant and current versions of the Transport and Main Roads Specifications and attached documentation. The works shall be carried out under the RoadTek Works Contract.
Project location is Bowen Road Bridge, Bowen Road (Ch:5,766km – Ch:5.999km), Townsville.

TenderHub gathers information continuously from a variety of sources. There may be delays between information being updated at the source and presented here. Always check with the source if you are concerned about currency or accuracy.

Key details

Source
QLD QTenders

Briefings & site visits

No briefings or site visits were listed for this tender.

Awarded suppliers

1

Contract awarded

$2,089,743 awarded to 1 supplier

  • N Q Civil Contractors