Goulburn Valley Water
Euroa Abbinga Reservoir No.2 Relining
Details
Description
All GVW Contractors who Tender for the work with a total amount of 100k or more will be required to have a third party certified safety system e.g. AS/NZS 4801:2001
Scope of Works:
The works of this contract comprise the construction of a new clay liner on the floor of the Abbinga No2 reservoir and associated works as shown on the drawings and accompanying specifications.
The works have been assigned to two separable portions:
1. Separable Portion A has been created to confirm the required volume of zone 1C material is available from the borrows identified on site (Abbinga 2 floor and yabby ponds).
2. Separable Portion B provides for the construction of a new liner and internal berms including supply of additional zone 1C material if required.
A compulsory site inspection with representatives of the Corporation is required.
GVW have a long and long policy; therefore all contractors attending the site must wear long sleeves shirt and long trousers – hats and HI VIS, eye protection & foot protection.
Location: Abbinga Reservoir, Millards Lane EUROA VIC 3666
Date & Time: 10:00AM Wednesday 13 March 2024
TenderHub gathers information continuously from a variety of sources. There may be delays between information being updated at the source and presented here. Always check with the source if you are concerned about currency or accuracy.
Key details
- Source
- Buying for Victoria
Briefings & site visits
No briefings or site visits were listed for this tender.
Awarded suppliers
1Contract awarded
$2,902,269 awarded to 1 supplier
See who else bid on this tender
Subscribers see every supplier who bid on this tender, plus its change history and a direct link to the source notice.