Hot Water Plant Electrification – CSIRO Newcastle (Construct only)

AwardedRequest for Tender

Details

Awarded

Description

CSIRO requires an experienced and qualified Mechanical Services Contractor to manage, construct and deliver the electrification of the gas fired primary- and secondary heat source at CSIRO’s Newcastle premises as per the design developed by CSIRO. This design:

(a) uses the two existing lead-lag reversible chillers in heat-pump mode for low-temperature heating-hot-water production, with one new water-to-water heat-pump/s installed in an existing plant room to boost the low-temperature heating hot water (HHW) to a higher temperature to meet existing field terminal device requirements.

(b) Decouples the domestic hot water (DHW) system from the HHW system to a standalone central potable DHW system. The non-potable DHW system will be decommissioned and replaced with instantaneous hot water units at nominated locations.

Locations

Request type

Request for Tender

TenderHub gathers information continuously from a variety of sources. There may be delays between information being updated at the source and presented here. Always check with the source if you are concerned about currency or accuracy.

Key details

Buyer
CSIRO
Source
AusTender

Briefings & site visits

No briefings or site visits were listed for this tender.

Awarded suppliers

1

Contract awarded

$2,728,404 awarded to 1 supplier