Awarded

Description

The dam on Bernacchis Creek, Maria Island was overtopped during a rare flood event in December 2009. A failure of the downstream embankment occurred. Repair of the downstream embankment of the dam and upgrading of the spillway to current design standards is required. The crest of the dam also requires raising to incorporate a greater depth of flow through the spillway prior to overtopping. Removal of the current bridge over the spillway and reinstating a pedestrian crossing at a higher level without any obstruction to the spillway weir.

Locations

Request type

Request for Quote

TenderHub gathers information continuously from a variety of sources. There may be delays between information being updated at the source and presented here. Always check with the source if you are concerned about currency or accuracy.

Key details

Source
Tasmanian Government Tenders

Briefings & site visits

No briefings or site visits were listed for this tender.

Awarded suppliers

1

Contract awarded

$191,877 awarded to 1 supplier

  • Treloar Transport

    $191,877